Another busy day at Fairway Drive.

Eric Busa designed, primed and put together some decorative trim to decorate the siding on the backside of the fireplace.  Also, the crew did tons of additional siding work in the part of the addition that includes the kitchen, upstairs bedroom, laundry and walk-in closet.  I also saw Anthony working hard preparing the ground for the front porch and grading the area where the current compressor sits.  Much of this is to also help prepare for hurricane Irene that is expected to arrive this weekend.  Eric also mentioned that he was having Anthony install some hurricane ties.  I came home too late to see with the limited lighting if it was done today.  I'll update with pics if they are in.

Here are some pics of the outside progress:

Anthony's hard work shown as the area for the front porch is prepared:


Backyard view of the progress on the siding in the rear part of the addition:


Another:

Decorative trim for the backyard of the fireplace designed and installed by Eric Busa:


Eric priming the decorative trim:



No comments:

Post a Comment