Danny and the other person from Trillenium worked in 100+ degree temperatures to fill back the foundation. Eric Busa, while on the beach at the Cape, told me not to bring out any heineken lights :), however I couldn't help but bring out some bottles of water. They did it though; they filled everything back, and I got to see some great work with the escavator and the bobcat. They also poured in some rocks/gravel for the cement flooring (to be done later) as you can see in the pics of the garage.
Danny told me that he'll be back to do the drainage later during the project.
We drove down to a wedding in NYC knowing that the foundation walls are pretty much done! What a week! A lot was accomplished. Thanks everyone.
Here are some pics of the progress from Friday. Next week starts framing!
Our new two garage goes here!
Our backyard
nice view from corner of lot
No comments:
Post a Comment